How to tailor PRINCE2 ‘Closing a Project’

PRINCE2 Project Close

What is the purpose of this PRINCE2 process?

This process provides a tidy end to your projects. It provides a fixed point for acceptance of the high level deliverable /product of the project. It also looks back to the original objectives (detailed in the PID) to see if they have been achieved.

PRINCE2 Courses
Foundation, Practitioner & Professional
High Pass Rates, Low Class Numbers
Exam Pass Guarantee

From £700

What activities does PRINCE2 recommend?

  • Prepare planned closure     OR    Prepare premature closure
  • Hand over products
  • Evaluate the project
  • Recommend project closure

Things that MUST be done

Read more... (274 words, 1 image, estimated 1:06 mins reading time)

PRINCE2 Courses
Foundation, Practitioner & Professional
High Pass Rates, Low Class Numbers
Exam Pass Guarantee

From £700








Categories: PRINCE2

How to tailor PRINCE2 ‘Managing a Stage Boundary’

prince2 Stage Boundary

What is the purpose of this PRINCE2 process?

This process provides the board with sufficient information to make a decision on whether or not to commit further resources and continue with the project to the next stage.   There are two ways into this process, either because one stage is nearing the end and the next stage needs to be planned, or because there has been a significant problem and the project board has asked that some re-planning takes place, in the form of an exception plan.

What activities does PRINCE2 recommend?

  • Plan the next stage      OR      Product an exception plan
  • Update the project plan
  • Update the Business Case
  • Report stage end

Things that MUST be done

Read more... (476 words, 1 image, estimated 1:54 mins reading time)

Categories: PRINCE2

How to tailor PRINCE2 ‘Managing Product Delivery’

PRINCE2 Project Delivery

What is the purpose of this PRINCE2 process?

This process is said to ‘control the link’ between the project manager and team manager(s) / team member(s). It is the process that gets the specialist products / outputs created and checked for their quality. While this is going on the team manager / member also needs to report progress to the project manager. Within PRINCE2 this level of report is known as a ‘Checkpoint Report’

It is recognised that the project teams doing this may be within a different (external) organisation that may or may not be using PRINCE2.

What activities does PRINCE2 recommend?

  • Accept a Work Package
  • Execute a Work Package
  • Deliver a Work Package

Things that MUST be done

Read more... (373 words, 1 image, estimated 1:30 mins reading time)

Categories: PRINCE2

How to tailor PRINCE2 ‘Controlling a Stage’

PRINCE2 Control a Stage

What is the purpose of this PRINCE2 process?

There are two primary things going on in this process. 

Firstly – ‘normal progress’ which means instigating getting the specialist / technical work done through issue of work instructions (on a PRINCE2 project these are called Work Packages’), monitoring progress and reporting to the project board.   This process ensures that work on specialist products does not start until the project manager authorises it.

Second – looking out for and handling problems (risks, issues and changes).

What activities does PRINCE2 recommend?

  • Authorise a Work Package
  • Review Work Package Status
  • Receive Completed Work Package
  • Review the Stage Status
  • Report Highlights
  • Capture and Examine Issues and Risks
  • Escalate Issues and Risks
  • Take Corrective Action

Things that MUST be done

Read more... (337 words, 1 image, estimated 1:21 mins reading time)

Categories: PRINCE2

How to tailor PRINCE2 ‘Directing a Project’

PRINCE2 Directing a Project
 

What is the purpose of this PRINCE2 process?

This process covers the work of the project board and enables them to be accountable for the project.   The process covers the major decision making on the project and therefore provides direction and is where responsibility for day to day control is delegated to the project manager,

What activities does PRINCE2 recommend?

  • Authorise Initiation
  • Authorise a Project
  • Authorise a Stage or Exception Plan
  • Give ad-hoc direction
  • Authorise project closure

Things that MUST be done

Read more... (458 words, 1 image, estimated 1:50 mins reading time)

Categories: PRINCE2